Practices - Risk
23 free practice questions with explanations
PassNova has 23 free PRINCE2 Foundation practice questions on Practices - Risk, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Practices - Risk: example questions & answers
12 worked examples with answers and explanations below. Practise all 23 Practices - Risk questions free in the browser, with instant feedback on every answer.
What is the Risk theme about?
- AEliminating all uncertainty
- BIdentifying, analyzing, and responding to uncertainties✓
- CPreventing all problems
- DRisk management planning only
Answer: Risk management involves systematic identification and management of uncertainties.
What is a Risk in PRINCE2?
- AA problem that has occurred
- BAn uncertain event that could affect objectives✓
- CA danger to the team
- DA financial loss
Answer: A risk is an uncertain event that, if it occurs, would impact project objectives.
What is Risk Identification?
- AKnowing which risks are real
- BSystematically finding potential risks✓
- CAssigning risks to people
- DCreating risk documents
Answer: Risk Identification is the systematic process of finding potential uncertainties.
How should risks be identified?
- AOnly by the Project Manager
- BThrough brainstorming with the team and stakeholders✓
- CBy reading risk lists
- DIndependently
Answer: Risk identification should be collaborative involving those with knowledge.
What is Risk Analysis?
- AWriting about risks
- BAssessing probability and impact of identified risks✓
- CSolving problems
- DListing risks
Answer: Risk Analysis evaluates the likelihood and consequences of risks.
What are the typical risk response strategies in PRINCE2?
- AOnly avoid and reduce
- BAvoid, reduce, transfer, accept, share, exploit✓
- CHope nothing happens
- DIgnore and manage them later
Answer: PRINCE2 identifies six main response strategies for different risk situations.
What does 'Avoid' mean as a risk response?
- AHope it doesn't happen
- BChange the project to eliminate the risk source✓
- CAccept it will happen
- DTransfer it to someone else
Answer: Avoid means changing the project approach to eliminate the risk.
What does 'Reduce' mean as a risk response?
- AIgnore the risk
- BCut the project scope
- CTake actions to decrease probability or impact✓
- DEliminate the risk completely
Answer: Reduce means implementing controls to make the risk less likely or less severe.
What does 'Transfer' mean as a risk response?
- AMove it to another department
- BPass the risk responsibility to a third party (e.g., insurance)✓
- CIgnore it
- DMake it someone else's problem
Answer: Transfer means shifting risk ownership to someone who is better able to manage it.
What does 'Accept' mean as a risk response?
- APretend the risk doesn't exist
- BAcknowledge the risk and accept the consequences if it occurs✓
- CHire more people
- DIncrease the budget
Answer: Accept means deciding to tolerate the risk if it happens without preventive action.
What is the Risk Register?
- AA list of team members
- BA document recording all identified risks and responses✓
- CA budget document
- DA schedule
Answer: The Risk Register documents all risks, their analysis, and planned responses.
Who should update the Risk Register?
- AOnly the Project Manager
- BThe Project Manager with team input regularly✓
- CAnnually
- DNever
Answer: The Risk Register should be maintained as a living document throughout the project.