Practices - Progress
19 free practice questions with explanations
PassNova has 19 free PRINCE2 Foundation practice questions on Practices - Progress, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Practices - Progress: example questions & answers
12 worked examples with answers and explanations below. Practise all 19 Practices - Progress questions free in the browser, with instant feedback on every answer.
What is the Progress theme about?
- AMaking sure work is fast
- BMonitoring and controlling project progress against plans✓
- CReporting activity
- DScheduling only
Answer: Progress ensures the project stays on track and takes corrective action when needed.
What are Tolerances in PRINCE2?
- AAcceptable levels of variation from the plan✓
- BMistakes that are tolerated
- CQuality standards
- DBudget limits only
Answer: Tolerances define acceptable ranges for cost, time, quality, scope, benefit, and risk.
What should happen when tolerances are breached?
- ANothing, continue as is
- BEscalate to the Project Board as an Exception✓
- CReduce quality
- DExtend the deadline
Answer: When tolerances are breached, an Exception Report is escalated.
What is an Exception in the context of Progress?
- AA problem person
- BA situation where actual or forecast performance will breach tolerances✓
- CA rare event
- DAn unexpected occurrence
Answer: An Exception occurs when project performance falls outside acceptable limits.
What is Exception Management?
- AManaging difficult people
- BThe process of escalating and resolving exceptions✓
- CPreventing exceptions
- DDocumenting errors
Answer: Exception Management handles situations that exceed tolerances.
What is an Exception Report?
- AA problem report
- BA document escalating an exception situation to the Project Board✓
- CAn incident log
- DA risk notification
Answer: An Exception Report informs the Project Board of tolerance breaches.
What is a Stage Gate (Stage Boundary)?
- AA meeting room
- BThe point where one stage ends and the next begins✓
- CA security checkpoint
- DA quality inspection
Answer: A Stage Boundary is where the Project Board makes a decision to proceed, adjust, or stop.
What should happen at a Stage Boundary?
- ACelebrate completion
- BReview stage performance and decide on the next stage✓
- CTake a break
- DReport status only
Answer: Stage Boundaries involve governance decisions about continuing the project.
What are the typical types of reports in progress management?
- ADaily reports only
- BHighlight, Checkpoint, Stage, and Exception reports✓
- CWeekly meetings
- DEmail updates only
Answer: PRINCE2 uses different report types for different audiences and frequencies.
What is a Highlight Report?
- AA detailed status report
- BA brief summary report for senior management✓
- CA risk report
- DA quality report
Answer: A Highlight Report is a concise summary for the Project Board.
Who should receive progress reports?
- AOnly the Project Manager
- BStakeholders according to the Communication Plan✓
- CEveryone in the organization
- DJust senior management
Answer: Progress reporting should follow the agreed Communication Plan.
How often should progress be reported?
- ADaily
- BAccording to the plan and stakeholder needs✓
- CWeekly
- DMonthly only
Answer: Reporting frequency should be defined in the Communication Plan.