  1. What is the Progress theme about?

    • AMaking sure work is fast
    • BMonitoring and controlling project progress against plans
    • CReporting activity
    • DScheduling only

    Answer: Progress ensures the project stays on track and takes corrective action when needed.

  2. What are Tolerances in PRINCE2?

    • AAcceptable levels of variation from the plan
    • BMistakes that are tolerated
    • CQuality standards
    • DBudget limits only

    Answer: Tolerances define acceptable ranges for cost, time, quality, scope, benefit, and risk.

  3. What should happen when tolerances are breached?

    • ANothing, continue as is
    • BEscalate to the Project Board as an Exception
    • CReduce quality
    • DExtend the deadline

    Answer: When tolerances are breached, an Exception Report is escalated.

  4. What is an Exception in the context of Progress?

    • AA problem person
    • BA situation where actual or forecast performance will breach tolerances
    • CA rare event
    • DAn unexpected occurrence

    Answer: An Exception occurs when project performance falls outside acceptable limits.

  5. What is Exception Management?

    • AManaging difficult people
    • BThe process of escalating and resolving exceptions
    • CPreventing exceptions
    • DDocumenting errors

    Answer: Exception Management handles situations that exceed tolerances.

  6. What is an Exception Report?

    • AA problem report
    • BA document escalating an exception situation to the Project Board
    • CAn incident log
    • DA risk notification

    Answer: An Exception Report informs the Project Board of tolerance breaches.

  7. What is a Stage Gate (Stage Boundary)?

    • AA meeting room
    • BThe point where one stage ends and the next begins
    • CA security checkpoint
    • DA quality inspection

    Answer: A Stage Boundary is where the Project Board makes a decision to proceed, adjust, or stop.

  8. What should happen at a Stage Boundary?

    • ACelebrate completion
    • BReview stage performance and decide on the next stage
    • CTake a break
    • DReport status only

    Answer: Stage Boundaries involve governance decisions about continuing the project.

  9. What are the typical types of reports in progress management?

    • ADaily reports only
    • BHighlight, Checkpoint, Stage, and Exception reports
    • CWeekly meetings
    • DEmail updates only

    Answer: PRINCE2 uses different report types for different audiences and frequencies.

  10. What is a Highlight Report?

    • AA detailed status report
    • BA brief summary report for senior management
    • CA risk report
    • DA quality report

    Answer: A Highlight Report is a concise summary for the Project Board.

  11. Who should receive progress reports?

    • AOnly the Project Manager
    • BStakeholders according to the Communication Plan
    • CEveryone in the organization
    • DJust senior management

    Answer: Progress reporting should follow the agreed Communication Plan.

  12. How often should progress be reported?

    • ADaily
    • BAccording to the plan and stakeholder needs
    • CWeekly
    • DMonthly only

    Answer: Reporting frequency should be defined in the Communication Plan.