PRINCE2 Foundation

Practices - Plans

25 free practice questions with explanations

PassNova has 25 free PRINCE2 Foundation practice questions on Practices - Plans, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.

Sample questions

Practices - Plans: example questions & answers

12 worked examples with answers and explanations below. Practise all 25 Practices - Plans questions free in the browser, with instant feedback on every answer.

  1. What is the Plans theme about?

    • ACreating schedules only
    • BDefining what, how, when, and by whom work will be done
    • CEstimating costs
    • DResource allocation only

    Answer: Plans define the products, activities, resources, and schedule for the project.

  2. What is Product-Based Planning?

    • APlanning based on the business products
    • BPlanning based on the products to be delivered by the project
    • CPlanning the product launch
    • DFocusing on production processes

    Answer: Product-Based Planning focuses on defining outputs and then determining activities needed to create them.

  3. What is a Product Breakdown Structure (PBS)?

    • AA list of activities
    • BA hierarchical breakdown of all project products
    • CA schedule of deliverables
    • DA budget breakdown

    Answer: The PBS shows all products (outputs) of the project in a hierarchical structure.

  4. What is the relationship between PBS and WBS?

    • AThey are the same
    • BPBS is products; WBS is activities needed to create them
    • CWBS comes before PBS
    • DThey are unrelated

    Answer: PBS (products) is used to create WBS (activities/work).

  5. What is a Work Package?

    • AA project plan
    • BA group of related activities to be delivered as one unit
    • CA schedule
    • DA team meeting

    Answer: A Work Package is a group of related activities assigned to one Team Manager.

  6. Who should be involved in plan creation?

    • AJust the Project Manager
    • BAll relevant parties: PM, Team Managers, specialists
    • COnly the Executive
    • DThe finance department only

    Answer: Planning should be collaborative with all parties who will do or be affected by the work.

  7. What should the Project Plan include?

    • AActivities only
    • BBudget only
    • CScope, products, activities, schedule, resources, risks, quality
    • DSchedules only

    Answer: The Project Plan covers all aspects of how the project will be managed.

  8. What is a Stage Plan?

    • AA plan for the entire project
    • BA detailed plan for a specific stage
    • CA preliminary plan
    • DA review document

    Answer: A Stage Plan provides detailed planning for a single project stage.

  9. When should Stage Plans be created?

    • AAt the start of the project
    • BAt the start of each stage
    • COnly when needed
    • DAt project completion

    Answer: Stage Plans are created at or near the start of each stage with detailed planning for that stage.

  10. What is the purpose of the Project Approach document?

    • ATo define the strategy for managing the project
    • BTo list all activities
    • CTo estimate the budget
    • DTo define roles only

    Answer: The Project Approach describes how the project will be managed overall.

  11. How should resource requirements be planned?

    • AEstimate people needed only
    • BDefine all resources (people, equipment, budget) needed by phase
    • CAsk the team what they need
    • DUse historical data only

    Answer: Resource planning should comprehensively cover all types of resources needed.

  12. What is a Constraint in project planning?

    • AA requirement that cannot be changed
    • BA limitation that affects the plan (e.g., fixed date, budget)
    • CA risk
    • DA quality standard

    Answer: Constraints are fixed parameters (budget, schedule, scope) that limit planning options.

Start practising Practices - Plans →