Practices - Plans
25 free practice questions with explanations
PassNova has 25 free PRINCE2 Foundation practice questions on Practices - Plans, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Practices - Plans: example questions & answers
12 worked examples with answers and explanations below. Practise all 25 Practices - Plans questions free in the browser, with instant feedback on every answer.
What is the Plans theme about?
- ACreating schedules only
- BDefining what, how, when, and by whom work will be done✓
- CEstimating costs
- DResource allocation only
Answer: Plans define the products, activities, resources, and schedule for the project.
What is Product-Based Planning?
- APlanning based on the business products
- BPlanning based on the products to be delivered by the project✓
- CPlanning the product launch
- DFocusing on production processes
Answer: Product-Based Planning focuses on defining outputs and then determining activities needed to create them.
What is a Product Breakdown Structure (PBS)?
- AA list of activities
- BA hierarchical breakdown of all project products✓
- CA schedule of deliverables
- DA budget breakdown
Answer: The PBS shows all products (outputs) of the project in a hierarchical structure.
What is the relationship between PBS and WBS?
- AThey are the same
- BPBS is products; WBS is activities needed to create them✓
- CWBS comes before PBS
- DThey are unrelated
Answer: PBS (products) is used to create WBS (activities/work).
What is a Work Package?
- AA project plan
- BA group of related activities to be delivered as one unit✓
- CA schedule
- DA team meeting
Answer: A Work Package is a group of related activities assigned to one Team Manager.
Who should be involved in plan creation?
- AJust the Project Manager
- BAll relevant parties: PM, Team Managers, specialists✓
- COnly the Executive
- DThe finance department only
Answer: Planning should be collaborative with all parties who will do or be affected by the work.
What should the Project Plan include?
- AActivities only
- BBudget only
- CScope, products, activities, schedule, resources, risks, quality✓
- DSchedules only
Answer: The Project Plan covers all aspects of how the project will be managed.
What is a Stage Plan?
- AA plan for the entire project
- BA detailed plan for a specific stage✓
- CA preliminary plan
- DA review document
Answer: A Stage Plan provides detailed planning for a single project stage.
When should Stage Plans be created?
- AAt the start of the project
- BAt the start of each stage✓
- COnly when needed
- DAt project completion
Answer: Stage Plans are created at or near the start of each stage with detailed planning for that stage.
What is the purpose of the Project Approach document?
- ATo define the strategy for managing the project✓
- BTo list all activities
- CTo estimate the budget
- DTo define roles only
Answer: The Project Approach describes how the project will be managed overall.
How should resource requirements be planned?
- AEstimate people needed only
- BDefine all resources (people, equipment, budget) needed by phase✓
- CAsk the team what they need
- DUse historical data only
Answer: Resource planning should comprehensively cover all types of resources needed.
What is a Constraint in project planning?
- AA requirement that cannot be changed
- BA limitation that affects the plan (e.g., fixed date, budget)✓
- CA risk
- DA quality standard
Answer: Constraints are fixed parameters (budget, schedule, scope) that limit planning options.