Practices - Organizing: example questions & answers
2 worked examples with answers and explanations below. Try 15 PRINCE2 Foundation questions free in the browser; the full 19-question Practices - Organizing bank is part of PassNova Premium.
What is the organizing practice about in PRINCE2 7?
- ADefining the project's structure of accountability and responsibilities✓
- BSetting out the order in which the products will be built
- CManaging personnel files, pay and appraisals for the team
- DAgreeing the budget and tolerances for each management stage
Answer: The organizing practice defines and establishes the project's structure of accountability and responsibilities - who is involved and how they relate across the project ecosystem. Sequencing products belongs to the plans practice, tolerances to progress, and HR administration stays with line management.
What are the Three Project Interests?
- AExecutive, Manager, Team Member
- BPlanning, Control and Risk Management
- CBusiness, User, Supplier✓
- DCost, Time and Quality (the project triangle)
Answer: The three interests represent different perspectives: business value, user needs, and supply capacity.