Certification & Documentation
25 free practice questions with explanations
PassNova has 25 free 18th Edition Wiring Regs practice questions on Certification & Documentation, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Certification & Documentation: example questions & answers
12 worked examples with answers and explanations below. Practise all 25 Certification & Documentation questions free in the browser, with instant feedback on every answer.
What is an Electrical Installation Certificate (EIC)?
- AA test equipment brand
- BA certification confirming a new installation complies with BS 7671✓
- CAn insurance document
- DA maintenance log
Answer: An EIC certifies that initial verification has been completed and installation meets BS 7671.
What must be included on an EIC?
- AOnly the installer's name
- BDesigner, installer, inspector names; test results; description of work; and compliance declaration✓
- CJust a date
- DEquipment prices
Answer: EICs must contain detailed certification of design, installation, testing, and compliance.
What is a Minor Electrical Installation Works Certificate (MEIWC)?
- AA full installation certificate
- BCertification for non-notifiable minor electrical work, not requiring full EIC✓
- CAn equipment test certificate
- DNot used
Answer: MEIWCs certify minor works such as single circuit modifications.
What is an Electrical Installation Condition Report (EICR)?
- AA design document
- BThe report from periodic inspection of existing installations, detailing defects and recommendations✓
- CAn annual maintenance plan
- DA warranty document
Answer: EICRs document the condition of existing electrical systems and identify any defects.
What are the typical codes used in EICRs to classify defects?
- AA, B, C only
- BC1 (urgent), C2 (requires urgent attention), C3 (requires attention), and observations✓
- CJust Pass/Fail
- DColor coding only
Answer: EICR codes: C1 (dangerous), C2 (potentially dangerous), C3 (non-compliant), and observations.
Who can issue a valid EIC?
- AAnyone
- BA competent person or qualified electrician registered with a Part P scheme✓
- CInsurance company only
- DBuilding surveyor only
Answer: Valid EICs are issued by competent persons, typically registered electricians with schemes like NICEIC.
What information must be on a Schedule of Test Results (SOR)?
- AJust a project list
- BAll measured test values, dates, instrument used, and acceptance criteria for each test✓
- CEquipment serial numbers only
- DJust signatures
Answer: SOR documents all electrical test measurements and must show how results comply with BS 7671.
What is the relationship between an EIC and Part P Building Regulations?
- ANo relationship
- BEIC serves as evidence of Part P compliance for electrical work✓
- CPart P only applies to plumbing
- DEIC is not related to building codes
Answer: EICs provide evidence that electrical work has been done safely and complies with Building Regulations Part P.
How long should electrical installation documentation be retained?
- A1 year only
- BMinimum 7 years for future reference and legal purposes✓
- C3 years maximum
- DNo requirement
Answer: Electrical documentation should be retained for at least 7 years.
What must be documented for each protective device?
- AJust the type
- BRating, function, breaking capacity, and location✓
- COnly the manufacturer
- DNothing specific
Answer: Protective devices must be documented with type, rating, breaking capacity, and clear labeling.
What is the purpose of a cable schedule in electrical documentation?
- ACost tracking only
- BClear identification of all circuits, cable sizing, routes, and protection details✓
- CEquipment inventory
- DNo purpose
Answer: Cable schedules document all circuits with sizes, routes, and protection for maintenance and safety.
What must be documented regarding circuit loads?
- AJust the highest load
- BEstimated load in amps for each circuit, allowing verification of cable sizing✓
- CLoad is not documented
- DOnly three-phase loads
Answer: Circuit loads must be documented to verify cables are correctly sized.