What is the first consideration for any demolition project?
- ASpeed of completion
- BCost minimization
- CHazard surveys identifying asbestos, structures, services, contamination, and structural instability✓
- DEquipment availability
Answer: Pre-demolition surveys are essential to identify hazardous materials (asbestos, lead), active utilities, structural hazards, and environmental contaminants.
What is a confined space?
- AAny small room
- BA space not designed for occupancy with limited access and potential for hazardous atmospheres✓
- CA closet or cupboard
- DAny underground area
Answer: Confined spaces include tanks, vaults, chambers, and enclosed areas where oxygen-deficiency or toxic atmospheres can develop. Limited entry/exit complicates rescue.
What is required before entry to a permit-required confined space?
- AJust worker consent
- BHazard assessment, atmospheric monitoring, rescue plan, permit, and trained personnel✓
- COnly equipment provision
- DNothing special
Answer: Permit-required confined space entry requires: completed permit, atmosphere tested and acceptable, rescue equipment and personnel prepared, and competent supervision.
What are the hazards associated with asbestos in demolition?
- AAsbestos is harmless
- BInhalation causes mesothelioma, lung cancer, and asbestosis✓
- COnly a minor irritant
- DNo specific hazard
Answer: Asbestos fiber inhalation causes serious lung disease. Demolition of asbestos-containing materials requires licensed contractors and specialized procedures.
When should asbestos removal occur during demolition?
- ADuring general demolition
- BBefore any other demolition work begins✓
- CAfter demolition is complete
- DIt doesn't matter
Answer: Asbestos must be removed and properly disposed of BEFORE general demolition commences to prevent contamination and fiber release.
What is atmospheric monitoring in confined spaces testing for?
- ATemperature and humidity only
- BOxygen levels, toxic gases, and flammable atmospheres✓
- CAirflow speed
- DMoisture content only
Answer: Testing checks: adequate oxygen (19.5%-23.5%), absence of toxic gases (H2S, CO, etc.), and absence of flammable atmospheres (LEL limits).
What is a 'Hot Work Permit'?
- APermission to work in warm weather
- BAuthorization and precautions for work involving heat (welding, cutting, grinding) to prevent fires✓
- CA type of training course
- DNot required
Answer: Hot Work Permits authorize high-temperature work and require: fire watch personnel, removal of combustibles, sprinklers/extinguishers ready, and post-work checks.
What should be done with utilities before demolition begins?
- ALeave them active for convenience
- BDisconnect, cap, and secure all services (gas, electricity, water, drainage) per regulations✓
- COnly gas needs disconnection
- DUtilities don't matter
Answer: All live utilities must be identified, safely disconnected, and capped to prevent fire, explosion, electrocution, and contamination during demolition.
What is a confined space rescue plan?
- AOptional procedure
- BDocumented plan for rapid extraction of an incapacitated entrant with trained and equipped rescuers✓
- CJust having a first aider on site
- DNot necessary
Answer: Rescue plans must document: rescue method, trained rescuers, required equipment (harnesses, lines, ventilation), and coordination with emergency services.
What training is required for confined space entry personnel?
- ANo special training needed
- BHazard recognition, atmospheric testing, rescue procedures, emergency response, and permit use✓
- COnly equipment operation
- DGeneral safety only
Answer: Competent personnel must understand confined space hazards, recognize atmospheric dangers, perform testing correctly, and execute rescue procedures.
What is the purpose of a confined space entry permit?
- APermits not needed
- BAuthorize entry, confirm hazards assessed, controls implemented, and rescue available✓
- COptional paperwork
- DOnly verbal permission required
Answer: Confined space permits document: hazard identification, atmosphere testing results, rescue plan confirmation, and authorized entrant/attendant/rescue person appointment.
What pre-demolition survey must be completed before demolition starts?
- ASurveys not required
- BAsbestos survey mandatory; identifies asbestos-containing materials before disturbance✓
- COnly visual inspection needed
- DNo asbestos risks in construction
Answer: Licensed asbestos survey required before demolition. Identifies ACM (asbestos-containing materials), determines encapsulation or removal requirements per regulations.