CITB SSSTS

Demolition & Confined Spaces

19 free practice questions with explanations

PassNova has 19 free CITB SSSTS practice questions on Demolition & Confined Spaces, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.

Sample questions

Demolition & Confined Spaces: example questions & answers

19 worked examples with answers and explanations below. Practise them in the browser with instant feedback on every answer.

  1. What is the first consideration for any demolition project?

    • AWhether the required equipment and machinery is already available on site
    • BMinimising the overall cost of the demolition contract for the client
    • CHazard surveys identifying asbestos, structures, services, contamination, and structural instability
    • DThe speed at which the demolition contractor can complete the whole project

    Answer: Pre-demolition surveys are essential to identify hazardous materials (asbestos, lead), active utilities, structural hazards, and environmental contaminants.

  2. What is a confined space?

    • AA space not designed for occupancy with limited access and potential for hazardous atmospheres
    • BAny small room within a building, regardless of how it is ventilated or accessed
    • CAny underground area at all, regardless of its size, access points, or ventilation
    • DA closet or cupboard used for storage, which is always safe to enter without any checks

    Answer: Confined spaces include tanks, vaults, chambers, and enclosed areas where oxygen-deficiency or toxic atmospheres can develop. Limited entry/exit complicates rescue.

  3. What is required before entry to a permit-required confined space?

    • AJust the verbal consent of the worker who will be entering the space, given informally on the day
    • BThe worker's own common sense on the day is all that is required
    • CHazard assessment, atmospheric monitoring, rescue plan, permit, and trained personnel
    • DOnly the provision of basic personal protective equipment, without any atmospheric testing beforehand

    Answer: Permit-required confined space entry requires: completed permit, atmosphere tested and acceptable, rescue equipment and personnel prepared, and competent supervision.

  4. What are the hazards associated with asbestos in demolition?

    • AOnly a minor irritant to the skin, similar to ordinary household dust
    • BCompletely harmless once the building has been left vacant for more than a year
    • CNo specific hazard exists provided the material is left completely undisturbed
    • DInhalation causes mesothelioma, lung cancer, and asbestosis

    Answer: Asbestos fibre inhalation causes serious lung disease. Demolition of asbestos-containing materials requires licensed contractors and specialised procedures.

  5. When should asbestos removal occur during demolition?

    • AIt does not matter at what point removal happens during the project
    • BBefore any other demolition work begins
    • CAfter the rest of the demolition work has already been fully completed
    • DAt the same time as general demolition, so that both jobs finish together

    Answer: Asbestos must be removed and properly disposed of BEFORE general demolition commences to prevent contamination and fibre release.

  6. What is atmospheric monitoring in confined spaces testing for?

    • AOxygen levels, toxic gases, and flammable atmospheres
    • BTemperature and humidity levels only, to keep workers comfortable inside
    • CThe speed of airflow only, to confirm that ventilation fans are switched on
    • DThe moisture content of the air only, to check for potential water ingress

    Answer: Testing checks: adequate oxygen (19.5%-23.5%), absence of toxic gases (H2S, CO, etc.), and absence of flammable atmospheres (LEL limits).

  7. What is a 'Hot Work Permit'?

    • APermission to carry out work on site during unusually warm summer weather
    • BAuthorisation and precautions for work involving heat (welding, cutting, grinding) to prevent fires
    • CUnnecessary for any construction task at all, regardless of the tools used
    • DA type of training course that all site operatives must complete once a year

    Answer: Hot Work Permits authorise high-temperature work and require: fire watch personnel, removal of combustibles, sprinklers/extinguishers ready, and post-work checks.

  8. What should be done with utilities before demolition begins?

    • AOnly the gas supply needs disconnecting; other services can safely stay connected
    • BDisconnect, cap, and secure all services (gas, electricity, water, drainage) per regulations
    • CLeft active throughout demolition for the convenience of the site team
    • DUtilities do not need to be considered as part of demolition planning

    Answer: All live utilities must be identified, safely disconnected, and capped to prevent fire, explosion, electrocution, and contamination during demolition.

  9. What is a confined space rescue plan?

    • AUnnecessary provided the entrant is wearing appropriate personal protective equipment
    • BSimply having a qualified first aider present somewhere on the wider site
    • CDocumented plan for rapid extraction of an incapacitated entrant with trained and equipped rescuers
    • DAn optional procedure that is only written up if the client specifically requests it

    Answer: Rescue plans must document: rescue method, trained rescuers, required equipment (harnesses, lines, ventilation), and coordination with emergency services.

  10. What training is required for confined space entry personnel?

    • ATraining limited to operating entry equipment, with no other topics covered
    • BWhatever training all workers already receive is enough
    • CHazard recognition, atmospheric testing, rescue procedures, emergency response, and permit use
    • DGeneral site safety induction only, with no confined-space-specific content

    Answer: Competent personnel must understand confined space hazards, recognise atmospheric dangers, perform testing correctly, and execute rescue procedures.

  11. What is the purpose of a confined space entry permit?

    • AAuthorise entry, confirm hazards assessed, controls implemented, and rescue available
    • BAn optional form that adds administrative delay without improving safety in any meaningful way
    • CA verbal nod from the site foreman is all that is legally required before entering a confined space
    • DConfined space entry needs no formal authorisation as long as the entrant feels confident

    Answer: Confined space permits document: hazard identification, atmosphere testing results, rescue plan confirmation, and authorised entrant/attendant/rescue person appointment.

  12. What pre-demolition survey must be completed before demolition starts?

    • AA quick visual walk-through by the site manager is enough to rule out hazardous materials
    • BA structural photograph of the building's exterior is sufficient evidence before demolition
    • CAsbestos survey mandatory; identifies asbestos-containing materials before disturbance
    • DAsbestos was fully removed from all UK buildings decades ago, so no survey is required

    Answer: Licensed asbestos survey required before demolition. Identifies ACM (asbestos-containing materials), determines encapsulation or removal requirements per regulations.

  13. What hazards exist in confined spaces?

    • AConfined space hazards build up gradually over several hours, giving ample time to react
    • BDust inhalation is the only meaningful risk, since most confined spaces are well ventilated
    • CConfined spaces carry no greater risk than any other enclosed room found on a typical site
    • DOxygen depletion, toxic gases, engulfment, and atmospheric pressure changes; rapid incapacitation

    Answer: Confined space hazards develop rapidly. Oxygen below 19.5% causes unconsciousness in seconds. Prohibition on entry without: atmosphere testing, rescue plan, and trained attendant.

  14. What is atmospheric monitoring in confined spaces?

    • AContinuous testing of oxygen, toxic gases, and combustible vapors before and during entry
    • BA single test taken before entry is sufficient, with no further monitoring needed inside
    • CAir conditions inside a confined space remain fixed once the initial entry check is complete
    • DMonitoring equipment is only required in spaces below ground, not in elevated tanks or vessels

    Answer: Continuous monitoring required: oxygen (19.5-23.5%), hydrogen sulfide (<10 ppm), carbon monoxide (<35 ppm), combustible vapors (<25% LEL). Alarms set for deviations.

  15. What is a rescue plan for confined space entry?

    • ABystanders and passing colleagues can always be relied upon to organise an effective rescue if something goes wrong
    • BOnly required when the confined space in question is deeper than roughly three metres below ground level surface
    • CDocument detailing rescue methods, trained personnel, equipment, and communication systems before entry
    • DUnnecessary provided the entrant carries a mobile phone to call for help if needed

    Answer: Rescue plans must identify: rescue method (tripod/harness), trained rescuers on standby, retrieval equipment tested, and communication between entrant and attendant.

  16. What asbestos removal procedures must be followed?

    • AAsbestos-containing material can be safely handled by any trained site operative without needing a specialist license
    • BAsbestos can be removed using the same methods and tools as any other demolition waste
    • CLicensed contractor, sealed work area, negative pressure ventilation, wet methods, and proper waste containment
    • DSmall quantities of asbestos can legally be removed by the ordinary site team without any specialist training or license

    Answer: Licensed asbestos contractor required. Procedures: work area isolation, negative pressure ventilation, wet removal methods, HEPA filtration, and certified disposal.

  17. What is competent person role in confined space work?

    • ATrained individual authorising entry, assessing hazards, ensuring monitoring, and coordinating rescue
    • BA purely administrative title with no real safety responsibilities on a confined space job
    • CAny available worker can take on the role, since competence is not a legal requirement
    • DEntry can be approved by whoever is on site at the time, regardless of training or experience

    Answer: Competent person must: understand confined space hazards, authorise entry, ensure atmosphere testing, verify rescue plan activation, and monitor throughout work.

  18. What hazards develop during building demolition?

    • ADust, asbestos release, structural collapse, noise, vibration, and buried hazards requiring planning
    • BDemolition can proceed on standard risk assessments used for general site work, since the hazards are no different from routine construction activity
    • CDust suppression is the main concern, so provided water spray is used continuously no separate asbestos survey or structural assessment is required
    • DOnce services are disconnected and the site fenced off, demolition presents minimal further risk

    Answer: Demolition hazards require: asbestos survey, structural analysis, dust suppression (water spray), noise control, vibration monitoring, and demolition sequence planning.

  19. What is the maximum safe duration for continuous confined space entry?

    • AWorkers may remain inside for as long as the task requires provided they carry a personal gas monitor, without needing a dedicated attendant outside
    • BDuration is only restricted in spaces with a known history of toxic gas, while entries into spaces tested clear beforehand have no time restriction
    • CEntry duration is set by the permit issuer as a single fixed 4-hour shift regardless of atmosphere, since gas testing at the start covers the whole period
    • DDepends on atmosphere; limit entries, use rotation, and ensure attendant monitoring throughout

    Answer: Continuous entry limits vary by atmosphere/conditions but typically short duration (30-60 min) with rotation, rest periods, and mandatory attendant supervision throughout.

Start practising Demolition & Confined Spaces →