  1. What is the main health and safety purpose of site hoarding?

    • AKeeping unauthorised people, particularly children, out of a dangerous place
    • BScreening the works from view so that neighbours are not disturbed by them
    • CProviding a surface for site signage and the principal contractor's branding
    • DPreventing materials and plant from being stolen outside working hours

    Answer: A construction site is an attractive and lethal playground. The duty to secure it is a health and safety duty owed to people who are not your workers, and children are the group most often killed by unsecured sites. Security against theft is a real benefit but it is not why the law requires it.

  2. Which of these must be in place before construction work starts on a new site?

    • AA finished construction phase plan covering every single activity across the whole project
    • BWelfare facilities, defined access and egress, traffic routes and emergency arrangements
    • CA full set of method statements signed by every operative who will attend the site
    • DThe client's written confirmation that the agreed programme allows for weather delays and holidays

    Answer: Set-up is where a site manager's job begins. Welfare has to be available from day one rather than arriving in week three, and access, traffic routes and emergency arrangements have to exist before anyone is exposed to them. The construction phase plan develops as the project does; it does not have to cover year two before week one can start.

  3. Why are vehicle and pedestrian routes planned at the set-up stage rather than later?

    • AThe routes determine the size of the site hoarding that will need to be ordered
    • BTraffic routes must be agreed with the local authority before the site can open
    • CRetro-fitting segregation once work has started is far harder and often not done
    • DPlanning them early means fewer deliveries will be needed during the project

    Answer: Once materials are stacked, cabins are sited and a compound is established, the space to put in a proper one-way circuit and a segregated walkway has gone. Sites that end up with people and plant sharing a route usually got there by default rather than by decision.

  4. What must a site induction cover?

    • AThe disciplinary procedure that applies if site rules are broken during the works
    • BA general summary of health and safety law and the worker's duties under it
    • CThe contents of the construction phase plan, read through in full with every new worker
    • DThe hazards on this site, the site rules, emergency arrangements and where welfare is

    Answer: An induction is site-specific and short enough to be remembered: what will hurt you here, what the rules are, what to do if the alarm sounds, where the toilets and first aid are, and who to tell. Generic legal background belongs in training, not at the gate, and reading a plan aloud guarantees nobody retains any of it.

  5. Why is securing the site a health and safety duty rather than only a commercial one?

    • AThe duty extends to people who are not workers, including trespassers and children
    • BInsurers require perimeter security before they will cover a construction project
    • CUnsecured sites attract fly-tipping, which creates an environmental offence
    • DStolen plant is often recovered damaged and then used in an unsafe condition

    Answer: Health and safety law protects people affected by the work, not just those doing it. A child who gets through a gap in the hoarding and falls into an excavation is squarely within that duty, and prosecutions follow. Theft and fly-tipping are real problems but they are not the reason the duty exists.

  6. What information should be displayed at the site entrance?

    • AThe full risk assessment for every activity being carried out on site
    • BSite rules, the PPE required, and who to report to on arrival
    • CThe names and home contact details of all first aiders and fire marshals
    • DA copy of the employer's liability insurance certificate and the F10 form

    Answer: Entrance signage tells a visitor or a new delivery driver what they need in the first thirty seconds: you are entering a construction site, this is the PPE, these are the rules, report here. Detailed risk assessments are for the people doing the work; personal contact details do not belong on a public boundary.