What is 'environmental management' in construction?
- AA requirement that applies only to projects above a set contract value or those needing full planning consent
- BControlling construction impacts on the environment: waste, pollution, water, ecosystems, and air quality✓
- COnly tree planting
- DIrrelevant to construction
Answer: Environmental management in construction addresses: waste management, pollution prevention, water management, dust/noise control, and ecological protection.
What is the 'waste hierarchy' in environmental management?
- ALandfill first
- BAny order will do
- CPrevent, reduce, reuse, recycle, recovery, and disposal as last resort✓
- DOnly recycling
Answer: Waste hierarchy (from best to worst): Prevention, Reduction, Reuse, Recycling, Energy recovery, Disposal. Each should be pursued in order before moving to the next.
What is 'duty of care' regarding construction waste?
- AOnly for hazardous waste
- BA duty that passes to the licensed waste carrier as soon as the loaded skip has left the site gate for the transfer station
- COnly if visible waste
- DLegal obligation to handle, store, and dispose of waste responsibly using licensed contractors and documentation✓
Answer: Duty of care for waste requires: proper containment, segregation, storage (secure and protected), use of licensed waste contractors, and documentation of waste transfer.
What is a 'Site Waste Management Plan' (SWMP) and what does it cover?
- ADocument planning waste segregation, reuse, recycling, and disposal routes for different waste streams✓
- BA record of the skip collections booked during the project, which is kept for the client's final account only
- CA plan needed only on projects above a set contract value, agreed between the client and building control
- DA voluntary document with no bearing on compliance, prepared only when the client asks for one at tender
Answer: A SWMP identifies: waste types likely, minimization strategies, reuse/recycling opportunities, licensed contractors, disposal routes, and monitoring procedures.
What are 'construction waste' types and segregation requirements?
- AOnly hazardous waste needs segregating; inert and general waste may be mixed together in a single skip
- BSegregation is dispensed with provided the waste is taken away by a registered carrier under a transfer note
- CWood, metals, plastics, concrete, brick, insulation; segregation required for recovery/recycling✓
- DAll waste is the same
Answer: Construction waste types: concrete, brick, soil, wood, metals, plastics, plasterboard, insulation. Segregation enables recycling: metals can be 95% recovered, wood 95%, concrete 95%.
What is 'pollution prevention' in construction?
- APreventing soil, water, and air pollution through spill control, dust management, and proper chemical storage✓
- BOnly for chemical spills
- CA low priority
- DOnly after a spill occurs
Answer: Pollution prevention includes: secondary containment for fuels/oils, proper drainage, dust suppression, chemical storage (labeling, segregation), and spill response procedures.
What is 'dust control' and what methods are used?
- AOnly on windy days
- BOf minor concern
- COnly sweeping
- DMethods to minimize dust: water spraying, extraction systems, barriers, and work scheduling✓
Answer: Dust control measures: water spraying (damping down), local extraction, hoarding/barriers, work scheduling (avoid dusty tasks in high wind), and respiratory protection.
What is 'noise pollution' control in construction?
- ALimiting noise impact on neighbors through equipment selection, silencers, screening, and restricted hours✓
- BLeft uncontrolled
- COnly ear protection
- DOnly for residential areas
Answer: Noise control: quieter equipment, silencers, acoustic screening, work hour restrictions, monitoring, and neighbor notification. Limits typically 75-85 dB during day, lower at night.
What is 'water management' in construction environmental protection?
- AControls needed only on large sites, as run-off from a small site is too little to pollute a nearby watercourse
- BPumping any standing water off the site and into the nearest surface water drain as quickly as it can be done
- CProtecting water from pollution: silt fences, settling tanks, spill containment, and controlling run-off✓
- DOnly during rain
Answer: Water protection includes: intercepting silt/sediment (silt fences, settling ponds), preventing fuel/chemical spills (containment), managing surface water, and dewatering control.
What is the Environmental Protection Act 1990 and its relevance to construction?
- AInapplicable
- BOnly for demolition
- COnly for large developments
- DAct providing framework for waste management, pollution control, and environmental duties✓
Answer: EPA 1990 establishes: waste management duties, pollution controls, and requires waste management licenses for certain activities. All construction must comply.
What is 'ecological impact' and when is an assessment needed?
- APotential effects on wildlife/habitats; assessment needed for large projects, sensitive locations, or protected species✓
- BA side issue
- COnly if ponds present
- DAn assessment needed only where a building over a certain footprint is proposed on an undeveloped greenfield site rather than on brownfield land
Answer: Ecological surveys and impact assessments are needed for projects affecting: protected species, designated habitats, water bodies, woodlands, or large sites. Mitigation is required.
What are 'hazardous construction wastes' requiring special handling?
- AOnly substances labelled as very toxic, since anything else can be dealt with in the site's general skip
- BAsbestos, paints, solvents, oils, and batteries requiring licensed disposal and documentation✓
- COrdinary construction rubble and offcuts, which the site team may sort and skip without any special licence
- DAsbestos alone, since paints, solvents and used oils may all be placed in the general waste skip
Answer: Hazardous wastes in construction include: asbestos (licensed disposal), oils/fluids, paints/solvents, batteries, fluorescent tubes (mercury), and PCBs. These require special contracts and tracking.
What is 'air quality' management in construction?
- AIrrelevant on construction sites, where work in the open air keeps emissions below any harmful level
- BMonitoring and controlling emissions: dust, fumes from equipment, and vehicle emissions✓
- CAn issue only on sites inside a city, where an air quality management area has been declared
- DControls limited to exhaust emissions from plant engines, since dust and fumes are not air quality issues
Answer: Air quality management: diesel engine controls (SCR filters), dust suppression, equipment maintenance, traffic management, and monitoring of air quality impacts.
What is 'sustainable construction' and how is it practiced?
- AOnly for certified buildings
- BMinimizing environmental impact through waste reduction, recycling, sustainable materials, and energy efficiency✓
- COnly avoiding materials
- DImpossible in construction
Answer: Sustainable construction: source sustainably-certified materials, minimize waste, maximize recycling, use renewable energy where possible, and reduce water use.
What is 'environmental impact assessment' (EIA) and when is it required?
- AOptional
- BAn assessment required only before demolition work, because building a new structure has no lasting environmental impact of its own
- COnly for mining
- DAssessment of project impacts on environment; required for large projects, sensitive locations, and Schedule 1/2 developments✓
Answer: EIA is required under Town and Country Planning (Environmental Impact Assessment) Regulations for certain projects (Schedule 1: always; Schedule 2: if threshold exceeded).
What must be included in an 'Environmental Management Plan'?
- AWaste arrangements only, since pollution, ecology and monitoring are covered by the planning conditions attached to the site
- BA short statement of general intent signed by a director, with the detail left to individual site teams to work out for themselves
- CWaste management, pollution prevention, air/water/soil protection, ecological measures, monitoring, and responsibilities✓
- DA plan needed only on projects above a set contract value, where the client requires one as part of the tender documentation
Answer: Environmental Management Plans should detail: waste management (segregation, disposal), pollution prevention (spill control, dust, noise), resource use (water, energy), and monitoring procedures.
What is 'contaminated land' and what are remediation requirements?
- ALand where contamination is visible at the surface, dealt with by covering it over with clean imported topsoil and turf
- BUnimportant
- CLand with harmful substances; requires assessment and remediation to prevent harm to human health or ecosystems✓
- DOnly from spills
Answer: Contaminated land (Environmental Protection Act 1990) requires: historical survey, risk assessment, remediation if necessary, and safe management/encapsulation if left in place.
What is 'Protected Species' in environmental law and contractor obligations?
- AOutside contractors' remit
- BNesting birds only, since bats, badgers and great crested newts are matters dealt with entirely by the local planning authority
- CSpecies legally protected (newts, bats, badgers); contractors must avoid harm and get licenses for necessary disturbance✓
- DOnly during breeding season
Answer: Protected species (Wildlife and Countryside Act 1981): badgers, bats, great crested newts, nesting birds. Contractors must: avoid harm, get licenses for disturbance, and implement mitigation.
What is 'fuel and oil management' on construction sites?
- AArrangements needed only for plant with large fuel tanks, as small bowsers and jerrycans present no real risk of pollution
- BSecure storage with secondary containment, spill prevention procedures, fueling away from water, and safe disposal✓
- CA trivial matter
- DDiesel fuel only, since hydraulic oils and greases are not classed as polluting if they are spilt on the ground on site
Answer: Fuel/oil management: secondary containment (bunds) holding 110% of largest container, storage away from water, labeling, spill kits, regular inspections, and safe fueling procedures.
What does environmental legislation require regarding 'environmental compliance' on construction sites?
- ACompliance needed only on large sites, since smaller projects fall outside the scope of environmental legislation
- BOnly main legislation
- CMeeting the main statutory duties only, since planning conditions and permits are entirely the client's concern
- DCompliance with all applicable laws: EPA, WAHR, EIA, DSEAR, planning conditions, and environmental permits✓
Answer: Construction must comply with: Environmental Protection Act, Water Resources Act, Environmental Permitting Regulations, planning conditions, and site-specific environmental permits.