  1. What is 'environmental management' in construction?

    • AA requirement that applies only to projects above a set contract value or those needing full planning consent
    • BControlling construction impacts on the environment: waste, pollution, water, ecosystems, and air quality
    • COnly tree planting
    • DIrrelevant to construction

    Answer: Environmental management in construction addresses: waste management, pollution prevention, water management, dust/noise control, and ecological protection.

  2. What is the 'waste hierarchy' in environmental management?

    • ALandfill first
    • BAny order will do
    • CPrevent, reduce, reuse, recycle, recovery, and disposal as last resort
    • DOnly recycling

    Answer: Waste hierarchy (from best to worst): Prevention, Reduction, Reuse, Recycling, Energy recovery, Disposal. Each should be pursued in order before moving to the next.

  3. What is 'duty of care' regarding construction waste?

    • AOnly for hazardous waste
    • BA duty that passes to the licensed waste carrier as soon as the loaded skip has left the site gate for the transfer station
    • COnly if visible waste
    • DLegal obligation to handle, store, and dispose of waste responsibly using licensed contractors and documentation

    Answer: Duty of care for waste requires: proper containment, segregation, storage (secure and protected), use of licensed waste contractors, and documentation of waste transfer.

  4. What is a 'Site Waste Management Plan' (SWMP) and what does it cover?

    • ADocument planning waste segregation, reuse, recycling, and disposal routes for different waste streams
    • BA record of the skip collections booked during the project, which is kept for the client's final account only
    • CA plan needed only on projects above a set contract value, agreed between the client and building control
    • DA voluntary document with no bearing on compliance, prepared only when the client asks for one at tender

    Answer: A SWMP identifies: waste types likely, minimization strategies, reuse/recycling opportunities, licensed contractors, disposal routes, and monitoring procedures.

  5. What are 'construction waste' types and segregation requirements?

    • AOnly hazardous waste needs segregating; inert and general waste may be mixed together in a single skip
    • BSegregation is dispensed with provided the waste is taken away by a registered carrier under a transfer note
    • CWood, metals, plastics, concrete, brick, insulation; segregation required for recovery/recycling
    • DAll waste is the same

    Answer: Construction waste types: concrete, brick, soil, wood, metals, plastics, plasterboard, insulation. Segregation enables recycling: metals can be 95% recovered, wood 95%, concrete 95%.

  6. What is 'pollution prevention' in construction?

    • APreventing soil, water, and air pollution through spill control, dust management, and proper chemical storage
    • BOnly for chemical spills
    • CA low priority
    • DOnly after a spill occurs

    Answer: Pollution prevention includes: secondary containment for fuels/oils, proper drainage, dust suppression, chemical storage (labeling, segregation), and spill response procedures.

  7. What is 'dust control' and what methods are used?

    • AOnly on windy days
    • BOf minor concern
    • COnly sweeping
    • DMethods to minimize dust: water spraying, extraction systems, barriers, and work scheduling

    Answer: Dust control measures: water spraying (damping down), local extraction, hoarding/barriers, work scheduling (avoid dusty tasks in high wind), and respiratory protection.

  8. What is 'noise pollution' control in construction?

    • ALimiting noise impact on neighbors through equipment selection, silencers, screening, and restricted hours
    • BLeft uncontrolled
    • COnly ear protection
    • DOnly for residential areas

    Answer: Noise control: quieter equipment, silencers, acoustic screening, work hour restrictions, monitoring, and neighbor notification. Limits typically 75-85 dB during day, lower at night.

  9. What is 'water management' in construction environmental protection?

    • AControls needed only on large sites, as run-off from a small site is too little to pollute a nearby watercourse
    • BPumping any standing water off the site and into the nearest surface water drain as quickly as it can be done
    • CProtecting water from pollution: silt fences, settling tanks, spill containment, and controlling run-off
    • DOnly during rain

    Answer: Water protection includes: intercepting silt/sediment (silt fences, settling ponds), preventing fuel/chemical spills (containment), managing surface water, and dewatering control.

  10. What is the Environmental Protection Act 1990 and its relevance to construction?

    • AInapplicable
    • BOnly for demolition
    • COnly for large developments
    • DAct providing framework for waste management, pollution control, and environmental duties

    Answer: EPA 1990 establishes: waste management duties, pollution controls, and requires waste management licenses for certain activities. All construction must comply.

  11. What is 'ecological impact' and when is an assessment needed?

    • APotential effects on wildlife/habitats; assessment needed for large projects, sensitive locations, or protected species
    • BA side issue
    • COnly if ponds present
    • DAn assessment needed only where a building over a certain footprint is proposed on an undeveloped greenfield site rather than on brownfield land

    Answer: Ecological surveys and impact assessments are needed for projects affecting: protected species, designated habitats, water bodies, woodlands, or large sites. Mitigation is required.

  12. What are 'hazardous construction wastes' requiring special handling?

    • AOnly substances labelled as very toxic, since anything else can be dealt with in the site's general skip
    • BAsbestos, paints, solvents, oils, and batteries requiring licensed disposal and documentation
    • COrdinary construction rubble and offcuts, which the site team may sort and skip without any special licence
    • DAsbestos alone, since paints, solvents and used oils may all be placed in the general waste skip

    Answer: Hazardous wastes in construction include: asbestos (licensed disposal), oils/fluids, paints/solvents, batteries, fluorescent tubes (mercury), and PCBs. These require special contracts and tracking.

  13. What is 'air quality' management in construction?

    • AIrrelevant on construction sites, where work in the open air keeps emissions below any harmful level
    • BMonitoring and controlling emissions: dust, fumes from equipment, and vehicle emissions
    • CAn issue only on sites inside a city, where an air quality management area has been declared
    • DControls limited to exhaust emissions from plant engines, since dust and fumes are not air quality issues

    Answer: Air quality management: diesel engine controls (SCR filters), dust suppression, equipment maintenance, traffic management, and monitoring of air quality impacts.

  14. What is 'sustainable construction' and how is it practiced?

    • AOnly for certified buildings
    • BMinimizing environmental impact through waste reduction, recycling, sustainable materials, and energy efficiency
    • COnly avoiding materials
    • DImpossible in construction

    Answer: Sustainable construction: source sustainably-certified materials, minimize waste, maximize recycling, use renewable energy where possible, and reduce water use.

  15. What is 'environmental impact assessment' (EIA) and when is it required?

    • AOptional
    • BAn assessment required only before demolition work, because building a new structure has no lasting environmental impact of its own
    • COnly for mining
    • DAssessment of project impacts on environment; required for large projects, sensitive locations, and Schedule 1/2 developments

    Answer: EIA is required under Town and Country Planning (Environmental Impact Assessment) Regulations for certain projects (Schedule 1: always; Schedule 2: if threshold exceeded).

  16. What must be included in an 'Environmental Management Plan'?

    • AWaste arrangements only, since pollution, ecology and monitoring are covered by the planning conditions attached to the site
    • BA short statement of general intent signed by a director, with the detail left to individual site teams to work out for themselves
    • CWaste management, pollution prevention, air/water/soil protection, ecological measures, monitoring, and responsibilities
    • DA plan needed only on projects above a set contract value, where the client requires one as part of the tender documentation

    Answer: Environmental Management Plans should detail: waste management (segregation, disposal), pollution prevention (spill control, dust, noise), resource use (water, energy), and monitoring procedures.

  17. What is 'contaminated land' and what are remediation requirements?

    • ALand where contamination is visible at the surface, dealt with by covering it over with clean imported topsoil and turf
    • BUnimportant
    • CLand with harmful substances; requires assessment and remediation to prevent harm to human health or ecosystems
    • DOnly from spills

    Answer: Contaminated land (Environmental Protection Act 1990) requires: historical survey, risk assessment, remediation if necessary, and safe management/encapsulation if left in place.

  18. What is 'Protected Species' in environmental law and contractor obligations?

    • AOutside contractors' remit
    • BNesting birds only, since bats, badgers and great crested newts are matters dealt with entirely by the local planning authority
    • CSpecies legally protected (newts, bats, badgers); contractors must avoid harm and get licenses for necessary disturbance
    • DOnly during breeding season

    Answer: Protected species (Wildlife and Countryside Act 1981): badgers, bats, great crested newts, nesting birds. Contractors must: avoid harm, get licenses for disturbance, and implement mitigation.

  19. What is 'fuel and oil management' on construction sites?

    • AArrangements needed only for plant with large fuel tanks, as small bowsers and jerrycans present no real risk of pollution
    • BSecure storage with secondary containment, spill prevention procedures, fueling away from water, and safe disposal
    • CA trivial matter
    • DDiesel fuel only, since hydraulic oils and greases are not classed as polluting if they are spilt on the ground on site

    Answer: Fuel/oil management: secondary containment (bunds) holding 110% of largest container, storage away from water, labeling, spill kits, regular inspections, and safe fueling procedures.

  20. What does environmental legislation require regarding 'environmental compliance' on construction sites?

    • ACompliance needed only on large sites, since smaller projects fall outside the scope of environmental legislation
    • BOnly main legislation
    • CMeeting the main statutory duties only, since planning conditions and permits are entirely the client's concern
    • DCompliance with all applicable laws: EPA, WAHR, EIA, DSEAR, planning conditions, and environmental permits

    Answer: Construction must comply with: Environmental Protection Act, Water Resources Act, Environmental Permitting Regulations, planning conditions, and site-specific environmental permits.