PassNova has 33 free CAPM practice questions on Project Management Fundamentals, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.

Sample questions

Project Management Fundamentals: example questions & answers

Here are 6 example questions from this topic. Practise the full set of 33 free in the browser.

  1. What is the BEST definition of a project?

    • A An ongoing operational activity that produces the same output repeatedly
    • B A permanent department responsible for delivering routine business services
    • C A collection of unrelated tasks performed by a single individual
    • D A temporary endeavour undertaken to create a unique product, service, or result

    Answer: A project is temporary, meaning it has a defined beginning and end, and it creates a unique deliverable, which distinguishes it from ongoing operations.

  2. A program is BEST described as which of the following?

    • A A single project with a fixed budget
    • B A routine maintenance schedule for operations
    • C A group of related projects managed in a coordinated way to obtain benefits not available from managing them individually
    • D A document that lists all organisational risks

    Answer: A program is a group of related projects managed together to achieve benefits and control that would not be possible if they were managed separately.

  3. Which document formally authorises the existence of a project and gives the project manager authority to apply resources?

    • A Project management plan
    • B Scope statement
    • C Work breakdown structure
    • D Project charter

    Answer: The project charter formally authorises the project and gives the project manager the authority to apply organisational resources to project activities.

  4. In which process group is the project charter typically developed?

    • A Executing
    • B Closing
    • C Initiating
    • D Planning

    Answer: The project charter is created during the Initiating process group, which formally starts the project or a phase.

  5. Which of the following lists the five process groups in the correct sequence?

    • A Planning, Initiating, Executing, Closing, Monitoring and Controlling
    • B Initiating, Planning, Executing, Monitoring and Controlling, Closing
    • C Initiating, Executing, Planning, Closing, Monitoring and Controlling
    • D Executing, Initiating, Planning, Monitoring and Controlling, Closing

    Answer: The five process groups are Initiating, Planning, Executing, Monitoring and Controlling, and Closing, though they often overlap and iterate.

  6. Who is primarily accountable for leading the project team and achieving the project objectives?

    • A The functional manager
    • B The project manager
    • C The end customer
    • D The project sponsor

    Answer: The project manager is the person assigned by the performing organisation to lead the team and is responsible for achieving the project objectives.