Predictive Plan-Based Methodologies
75 free practice questions with explanations
PassNova has 75 free CAPM practice questions on Predictive Plan-Based Methodologies, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Predictive Plan-Based Methodologies: example questions & answers
Here are 6 example questions from this topic. Practise the full set of 75 free in the browser.
-
A predictive (waterfall) life cycle is MOST appropriate when which condition is true?
- A Requirements are highly uncertain and expected to change frequently
- B Requirements are well understood and stable, and scope can be defined up front ✓
- C The customer wants to inspect a working product every two weeks
- D The team has no documented plan and prefers to improvise
Answer: Predictive life cycles work best when requirements are clear and stable, allowing scope, schedule, and cost to be defined early and changes to be minimised.
-
What is a work breakdown structure (WBS)?
- A A list of project risks ranked by probability
- B A bar chart showing activity start and finish dates
- C A hierarchical decomposition of the total scope of work to be carried out by the project team ✓
- D A register of all project stakeholders
Answer: The WBS is a deliverable-oriented hierarchical decomposition of the total project scope into smaller, more manageable components.
-
The lowest level of a work breakdown structure is known as a what?
- A Milestone
- B Deliverable phase
- C Control account
- D Work package ✓
Answer: A work package is the lowest level of the WBS, for which cost and duration can be estimated and managed.
-
In schedule network analysis, the critical path is BEST described as which of the following?
- A The longest path through the network, which determines the shortest possible project duration ✓
- B The path with the most activities
- C The path that costs the most money
- D The path with the fewest dependencies
Answer: The critical path is the longest sequence of dependent activities and determines the earliest the project can finish; it has zero total float.
-
What does total float (slack) measure for an activity?
- A The amount of time the activity can be delayed without delaying the project end date ✓
- B The number of resources assigned to the activity
- C The quality tolerance allowed for the deliverable
- D The amount of money budgeted for the activity
Answer: Total float is the amount of time an activity can be delayed from its early start without delaying the project completion date.
-
A Gantt chart is MOST commonly used to display which of the following?
- A The organisational hierarchy of the project team
- B Project costs broken down by category
- C The probability and impact of each risk
- D Project activities plotted against a timeline with bars showing duration ✓
Answer: A Gantt chart is a bar chart that shows project activities against a calendar timeline, making start dates, durations, and overlaps easy to see.