Agile Frameworks & Methodologies
50 free practice questions with explanations
PassNova has 50 free CAPM practice questions on Agile Frameworks & Methodologies, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Agile Frameworks & Methodologies: example questions & answers
Here are 6 example questions from this topic. Practise the full set of 50 free in the browser.
-
Which of the following is one of the four core values of the Agile Manifesto?
- A Individuals and interactions over processes and tools ✓
- B Contract negotiation over customer collaboration
- C Following a plan over responding to change
- D Comprehensive documentation over working software
Answer: The Agile Manifesto values individuals and interactions over processes and tools, while still recognising value in the items on the right.
-
In Scrum, who is accountable for managing and prioritising the product backlog?
- A The Product Owner ✓
- B The Development Team
- C The project sponsor
- D The Scrum Master
Answer: The Product Owner is accountable for maximising the value of the product by managing and ordering the product backlog.
-
What is the role of the Scrum Master?
- A To own and prioritise the product backlog
- B To serve the team as a facilitator and coach, removing impediments and upholding the Scrum framework ✓
- C To sign off the project budget
- D To assign tasks to developers and approve their work
Answer: The Scrum Master is a servant leader who coaches the team, facilitates events, and removes impediments so the team can be effective.
-
In Scrum, a time-boxed iteration during which a usable increment is created is called a what?
- A Milestone
- B Phase gate
- C Release
- D Sprint ✓
Answer: A sprint is a fixed time-box, usually one to four weeks, during which the team produces a potentially releasable product increment.
-
What is the PRIMARY purpose of the daily standup (daily scrum)?
- A To allow the development team to synchronise work and plan the next 24 hours ✓
- B To conduct performance reviews of team members
- C To negotiate the project contract
- D To give detailed status reports to senior management
Answer: The daily scrum is a short event for the development team to inspect progress toward the sprint goal and plan the work for the next day.
-
Which Scrum event is held at the end of a sprint to demonstrate the increment and gather stakeholder feedback?
- A Backlog refinement
- B Sprint planning
- C Sprint review ✓
- D Sprint retrospective
Answer: The sprint review is held at the end of the sprint to inspect the increment with stakeholders and adapt the product backlog as needed.