Governance: example questions & answers
3 worked examples with answers and explanations below. Try 15 PgMP questions free in the browser; the full 40-question Governance bank is part of PassNova Premium.
What is the PRIMARY purpose of program governance?
- ATo perform the detailed technical work of each component
- BTo eliminate the need for a program manager
- CTo provide the framework, decision-making authority, and oversight needed to guide the program toward its intended benefits within organizational policy✓
- DTo directly manage each team member's daily task list
Answer: Program governance provides the framework, decision rights, and oversight that guide the program toward its intended benefits within organizational policy; it does not replace the program manager or perform component-level technical work.
Who is typically ULTIMATELY accountable for enabling the program's success and realizing its benefits, even though the program manager runs day-to-day activities?
- AThe program sponsor✓
- BThe most junior component team member
- CAn external regulator
- DThe program's original vendor
Answer: The program sponsor holds ultimate accountability for enabling success and benefit realization, providing resources and championing the program, while the program manager handles day-to-day execution.
A program governance board's role at a scheduled phase-gate review is BEST described as:
- ADeciding whether the program should continue, be adjusted, or be stopped based on its alignment, performance, and continued business justification✓
- BPerforming the technical acceptance testing of each component's deliverables and formally signing off the test results before the phase gate is passed
- CWriting the program's detailed schedule
- DApproving each team member's individual timesheet
Answer: A phase-gate review is a governance decision point assessing alignment, performance, and business justification to decide whether the program continues, is adjusted, or stops.