Risk Assessment
25 free practice questions with explanations
PassNova has 25 free NEBOSH General Certificate practice questions on Risk Assessment, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Risk Assessment: example questions & answers
12 worked examples with answers and explanations below. Practise all 25 Risk Assessment questions free in the browser, with instant feedback on every answer.
What is the 5-step risk assessment process?
- AIdentify hazards, identify who is at risk, evaluate risk, implement controls, monitor and review✓
- BWrite a policy, train staff, inspect equipment, report incidents
- CAudit, document, review, approve, implement
- DPlan, do, check, act
Answer: The 5-step process is: 1) Identify hazards, 2) Identify who is at risk, 3) Evaluate risk, 4) Implement control measures, 5) Monitor and review.
What is a 'hazard'?
- AAnything with the potential to cause harm✓
- BAn incident that has occurred
- CA control measure
- DTraining material
Answer: A hazard is any source or situation with the potential to cause harm (e.g., electricity, asbestos, aggressive behaviour).
What is 'risk' in H&S terms?
- AThe combination of likelihood and severity of harm from a hazard✓
- BA potential hazard only
- CThe total number of hazards
- DThe cost of an incident
Answer: Risk is the likelihood of harm occurring combined with the severity of that harm.
In risk assessment, what is 'acceptability of risk'?
- AA risk is acceptable if the benefit of the activity outweighs the residual risk✓
- BAll risks must be eliminated completely
- COnly high risks matter
- DAcceptability depends on the cost
Answer: A risk is acceptable when it is reduced to a level where the benefit of the activity justifies the residual risk.
What is the 'hierarchy of control'?
- AA prioritised list: eliminate, substitute, engineer, administer, PPE✓
- BAn order for incident investigation
- CA structure for organizational responsibilities
- DA schedule for inspections
Answer: The hierarchy prioritises control methods from most to least effective: elimination first, PPE as a last resort.
What does 'elimination' mean in the hierarchy of control?
- ARemoving the hazard completely✓
- BMoving workers away from the hazard
- CUsing PPE
- DInstalling guards
Answer: Elimination means removing the hazard entirely (e.g., not using a hazardous chemical at all).
What does 'substitution' mean in the hierarchy of control?
- AReplacing a hazardous substance or process with a less hazardous alternative✓
- BMoving the hazard away
- CUsing PPE instead
- DReducing exposure time
Answer: Substitution replaces a hazard with something less dangerous (e.g., using a water-based cleaner instead of a toxic solvent).
What are 'engineering controls'?
- APhysical measures to prevent exposure or reduce the level of hazard (guards, ventilation, isolation)✓
- BProcedures and policies
- CPersonal protective equipment
- DTraining programs
Answer: Engineering controls use equipment or design to control hazards (e.g., local exhaust ventilation, machine guards, emergency stops).
What are 'administrative controls'?
- AProcedures, systems, rules and practices to reduce exposure (rotation, supervision, permits)✓
- BEquipment and machines
- CPersonal protective equipment
- DWritten policies only
Answer: Administrative controls include procedures, work practices, supervision and systems (e.g., lock-out/tag-out, permits to work, job rotation).
What is 'residual risk'?
- AThe risk remaining after control measures have been applied✓
- BThe original risk before assessment
- CRisks that cannot be identified
- DRisks created by control measures
Answer: Residual risk is the level of risk remaining after all feasible control measures have been implemented.
What is a 'dynamic assessment' or 'dynamic risk assessment'?
- AContinuous assessment of risk during an activity, adapted to changing circumstances✓
- BA risk assessment done every year
- CAn assessment using computers
- DAn external assessment only
Answer: Dynamic assessment means continuously monitoring and adjusting to risks as circumstances change (e.g., emergency response, rescue operations).
What is a 'safe system of work'?
- AAn integrated set of procedures and arrangements to control hazards and manage risks during an activity✓
- BA written policy document
- CWearing safety equipment
- DFollowing instructions only
Answer: A safe system of work integrates all necessary control measures (procedures, materials, training, equipment) to manage risks.