APM Project Fundamentals (PFQ)

Planning, Scheduling & Resource

26 practice questions with explanations — 15 free to try

PassNova has 26 APM Project Fundamentals (PFQ) practice questions on Planning, Scheduling & Resource, each with a clear explanation. A 15-question taster is free with no sign-up; the full bank is part of PassNova Premium. Updated for 2026.

Sample questions

Planning, Scheduling & Resource: example questions & answers

3 worked examples with answers and explanations below. Try 15 APM Project Fundamentals (PFQ) questions free in the browser; the full 26-question Planning, Scheduling & Resource bank is part of PassNova Premium.

  1. What does a work breakdown structure (WBS) primarily do?

    • ALists stakeholders in order of influence
    • BDecomposes the total scope of work into smaller, manageable work packages
    • CRecords identified project risks
    • DTracks daily team attendance

    Answer: A WBS hierarchically decomposes the total project scope into progressively smaller, manageable work packages to aid planning and control.

  2. On a network diagram, the critical path is:

    • AThe path that costs the least to complete
    • BAny path that contains a milestone
    • CThe path with the most activities on it, regardless of how long each of those activities takes to finish
    • DThe longest sequence of dependent activities that determines the shortest possible project duration

    Answer: The critical path is the longest chain of dependent activities; it sets the minimum project duration, and any delay on it delays the whole project.

  3. What is 'float' (slack) in a project schedule?

    • AThe amount of time an activity can be delayed without delaying the project (total float) or a successor
    • BThe number of resources assigned to a task
    • CThe profit margin on the project
    • DThe extra budget held in reserve

    Answer: Float (slack) is the amount of time an activity can be delayed without affecting the project completion date (total float) or its successor activities.

Start practising Planning, Scheduling & Resource →