Planning, Scheduling & Resource
26 free practice questions with explanations
PassNova has 26 free APM Project Fundamentals (PFQ) practice questions on Planning, Scheduling & Resource, each with a clear explanation. Practise them in the browser with instant feedback — 100% free, no sign-up, on any device. Updated for 2026.
Planning, Scheduling & Resource: example questions & answers
Here are 6 example questions from this topic. Practise the full set of 26 free in the browser.
-
What does a work breakdown structure (WBS) primarily do?
- A Lists stakeholders in order of influence
- B Decomposes the total scope of work into smaller, manageable work packages ✓
- C Records identified project risks
- D Tracks daily team attendance
Answer: A WBS hierarchically decomposes the total project scope into progressively smaller, manageable work packages to aid planning and control.
-
On a network diagram, the critical path is:
- A The path that costs the least to complete
- B Any path that contains a milestone
- C The path with the most activities regardless of duration
- D The longest sequence of dependent activities that determines the shortest possible project duration ✓
Answer: The critical path is the longest chain of dependent activities; it sets the minimum project duration, and any delay on it delays the whole project.
-
What is 'float' (slack) in a project schedule?
- A The amount of time an activity can be delayed without delaying the project (total float) or a successor ✓
- B The number of resources assigned to a task
- C The profit margin on the project
- D The extra budget held in reserve
Answer: Float (slack) is the amount of time an activity can be delayed without affecting the project completion date (total float) or its successor activities.
-
What is the purpose of a project baseline?
- A To provide an approved reference (e.g. for scope, schedule and cost) against which performance is measured ✓
- B To list every stakeholder's contact details
- C To replace the need for change control
- D To record the lowest acceptable quality level only
Answer: A baseline is the approved version of scope, schedule and/or cost used as a fixed reference point to measure and control progress against.
-
What does resource smoothing aim to achieve?
- A Removing all resources from the critical path
- B Increasing the project budget to its maximum
- C Completing the project as quickly as possible regardless of resource limits
- D Adjusting activities within their float to keep resource usage within set limits without delaying the end date ✓
Answer: Resource smoothing uses available float to level resource demand within agreed limits while keeping the planned completion date unchanged.
-
Which estimating approach uses data from past similar projects to estimate the current one?
- A Three-point estimating
- B Parametric estimating from unit rates only
- C Bottom-up estimating
- D Analogous (comparative) estimating ✓
Answer: Analogous (comparative) estimating draws on actual data from previous similar projects to produce an estimate, useful early when detail is limited.