Skip to main content
PMP

Planning: Scope, Schedule & Cost

46 practice questions with explanations — 15 free to try

3 of these 46 questions are in the free 15-question taster · the full topic is part of Premium

PassNova has 46 PMP practice questions on Planning: Scope, Schedule & Cost, each with a clear explanation. A 15-question taster is free with no sign-up; the full bank is part of PassNova Premium. Updated for 2026.

Sample questions

Planning: Scope, Schedule & Cost: example questions & answers

3 worked examples with answers and explanations below. Try 15 PMP questions free in the browser; the full 46-question Planning: Scope, Schedule & Cost bank is part of PassNova Premium.

  1. A project manager is decomposing the project scope into smaller components. The lowest level of the WBS that can be estimated and assigned is called a:

    • AMilestone
    • BControl account
    • CWork package✓
    • DActivity list

    Answer: A work package is the lowest level of the WBS at which cost and duration can be estimated and managed. It is the foundation for scheduling and assigning work.

  2. Activity B cannot start until Activity A finishes, and two extra days must pass before B can begin. This relationship is a:

    • AStart-to-Start with a lag of two days
    • BFinish-to-Finish with a lag of two days
    • CFinish-to-Start with a lag of two days✓
    • DFinish-to-Start with a lead of two days

    Answer: A Finish-to-Start dependency with a lag inserts a mandatory waiting period after the predecessor finishes before the successor starts. A lead would accelerate the successor, the opposite of this case.

  3. A project has earned value (EV) of $80,000 and actual cost (AC) of $100,000. What is the cost performance index (CPI)?

    • A1.25
    • B1.00
    • C0.50
    • D0.80✓

    Answer: CPI equals EV divided by AC, which is $80,000 / $100,000 = 0.80, indicating the project is over budget. A CPI below 1.0 signals cost overruns.

Start practising Planning: Scope, Schedule & Cost →