What is the main benefit, to a project, of having a communication plan?
- AIt removes the need to identify stakeholders
- BIt ensures the right information reaches the right people, at the right time, through the right channel, supporting engagement and decision-making✓
- CIt guarantees no conflict will ever arise
- DIt replaces the need for a risk register
Answer: A communication plan ensures relevant information reaches the right stakeholders at the right time through appropriate channels, supporting engagement, understanding and effective decision-making.
What is the relationship between stakeholder analysis and an effective communication management plan?
- AThey are unrelated activities carried out by different departments
- BStakeholder analysis is only completed after the communication plan is finalised
- CCommunication plans are drafted before any stakeholders have been identified
- DStakeholder analysis identifies who needs what information and how much influence they have, which then shapes the content, frequency and channel choices in the communication plan✓
Answer: Stakeholder analysis reveals stakeholders' interests, influence and information needs, and this directly informs how the communication plan tailors content, frequency and channels for each group.