Skip to main content
AgilePM Foundation

MoSCoW, Timeboxing & Practices

33 practice questions with explanations — 15 free to try

3 of these 33 questions are in the free 15-question taster · the full topic is part of Premium

PassNova has 33 AgilePM Foundation practice questions on MoSCoW, Timeboxing & Practices, each with a clear explanation. A 15-question taster is free with no sign-up; the full bank is part of PassNova Premium. Updated for 2026.

Sample questions

MoSCoW, Timeboxing & Practices: example questions & answers

3 worked examples with answers and explanations below. Try 15 AgilePM Foundation questions free in the browser; the full 33-question MoSCoW, Timeboxing & Practices bank is part of PassNova Premium.

  1. What does AgilePM recommend about the proportion of effort allocated to Must Have requirements within a Sprint, so that contingency is provided?

    • AMust Haves should be exactly 25% of the effort
    • BThe balance of Must Haves is left entirely to the team
    • CMust Haves should be no more than 60% of the effort✓
    • DMust Haves should always be 100% of the effort

    Answer: AgilePM guidance recommends Must Haves at no more than about 60% of effort, with around 20% Should Have and 20% Could Have, so the Could Haves provide a contingency that protects on-time delivery.

  2. Which MoSCoW category is most likely to be sacrificed first if a Sprint comes under time pressure?

    • AWon't Have this time
    • BMust Have
    • CShould Have
    • DCould Have✓

    Answer: Could Have requirements are desirable but not vital, so they act as the built-in contingency and are the first to be dropped to protect on-time delivery of the Must Haves.

  3. In AgilePM timeboxing, what is meant by the deadline of a Sprint being fixed?

    • AThe end date can be extended by the Project Manager if the highest-priority requirements are late
    • BThe end date is immovable, so scope is flexed via MoSCoW rather than moving the deadline✓
    • CThe Sprint has no defined end date and simply runs on until the planned work has been completed
    • DThe Could Have requirements have a fixed deadline within the Sprint, while the rest may slip

    Answer: A core idea of timeboxing is that the deadline is fixed and protected; if work is at risk, lower-priority requirements are dropped rather than extending the Sprint.

Start practising MoSCoW, Timeboxing & Practices →